A pilot project to generate electricity using a combination of wind and solar power has been shut down. The project's results showed lower power generation and higher costs compared to conventional solar systems. Installation costs were significantly higher, about 4.86 times more than traditional solar systems. The project generated 8,793 kWh of electricity over a period of time. Further details about the project, including its costs and assessment, are available. The total cost of the project was Rs 19.47 lakh.

The hybrid systems were installed in two sections. An agency was appointed to oversee the project.

The project's closure follows an assessment of its performance.