Mumbai Infra Update: GMLR Tunnel Boring Machine ‘Tulsi’ Completes 183-Metre Excavation, ‘Vihar’ Clears Key Test

Mumbai Infra Update: GMLR Tunnel Boring Machine ‘Tulsi’ Completes 183-Metre Excavation, ‘Vihar’ Clears Key Test
Photo: Free Press Journal · view original

Mumbai, October 19, 2026: The BMC has completed 183 metres of excavation using ‘Tulsi’, the first tunnel-boring machine (TBM) deployed for the twin tunnels beneath Sanjay Gandhi National Park (SNGP) as part of Phase 3(B) of the Goregaon-Mulund Link Road (GMLR) project. Meanwhile, the second TBM,...